Esterling - Time Study Model

Time Parameters

a

Average fraction of workday spent on administrative or other indirect work

t

Average duration of working interrupts (minutes)

r

Average recovery time after interruptions (minutes)

k

Number of interruptions/workday from project personnel

p

Number of interruptions/workday from non-project personnel

i

Indirect (overhead) cost/person expressed as fraction of base pay

d

Differential pay for overtime expressed as fraction of base pay

n

Number of people working in the project

g

Average number of overtime workhours per workday

 

Parameter

Range

Factory Workers

Programmers

Optimistic

Typical

Pessimistic

a

0 - 0,5

0.0

0.05

0.10

0.15

t

1 - 20

3

3

5

10

r

0.5 - 10

0.5

0.5

2.0

8.0

k

1 - 10

1

2

3

4

p

1 - 10

1

1

4

10

i

0.1 - 3

0.2

0.2

0.5

1.5

d

1 - 2

1.5

1

1

1.5

Parameter Description

 

 
 

Useful Working Time

w = 0.125 x [ 8 - 8a + g - (4r - p(t+r) - k(n-1)(t+r))/60 ]

T = 7 / ( 5nw)

ratio of calendar time to person-days to complete the project

c = ns(gd+ 8(1+i))

labor cost per work day for an average base salary s

e = nw / c

cost efficiency

C = c / (nw)

Project cost per person-day

 